Ariola and Kristoff debate capital project backlog and deferred maintenance

New York City Council · Jun 1, 2026 · starts 6:24:39 · 4 min 32 sec

Ariola raises concerns about deferred maintenance and capital projects pushed to out-years. Kristoff reports $994M for facilities across FY26-35, with $553M in the first five years, noting capital funding has nearly doubled over five years. Ariola presses on why firehouses remain in disrepair despite funding.

Joann Ariola

We're going to move on to, well, does the fire department have a platform that tracks and prioritizes work order requests, assessments, and resolution?

Unidentified speaker

Yes, we do.

Unidentified speaker

We have an asset management program.

Joann Ariola

I'm sorry, I didn't hear you.

Joann Ariola

I'm sorry.

Unidentified speaker

Yes, we do.

Unidentified speaker

We have an EAM.

Unidentified speaker

It's an asset management program.

Joann Ariola

Okay, and you use the Niedermann systems as well, or?

Unidentified speaker

Yes, we have Niedermann systems.

Joann Ariola

Niedermann systems.

Joann Ariola

And how many systems are inoperable right now?

Unidentified speaker

Zero.

Joann Ariola

Zero.

Joann Ariola

They're all operable?

Unidentified speaker

Yes.

Joann Ariola

Oh, okay.

Joann Ariola

All right.

Joann Ariola

Okay.

Joann Ariola

Let's see.

Joann Ariola

The FDNY has publicly cited a substantial backlog of capital projects.

Joann Ariola

facilities funding to the out years.

Joann Ariola

Meanwhile, we have identified a list of firehouses with severely deteriorating roofs, of which only six projects have been funded to date.

Joann Ariola

We have serious concerns about deferred maintenance.

Joann Ariola

The adequacy of near-term capital funding, and the administration's reliance on council member allocations to fund what could be core infrastructure.

Joann Ariola

Do you have an amount needed to repair all capital projects, and have you requested that from the administration?

Unidentified speaker

So to talk about facilities funding in general, so our current capital plan includes $994 million for facilities across FY26 through FY35.

Unidentified speaker

The funding is split pretty evenly between the first five years and the last five years.

Unidentified speaker

It's actually slightly front-loaded.

Unidentified speaker

So FY26 through FY30 is $553 million, whereas FY31 through FY35 is $441 million.

Unidentified speaker

But even with that, I mean, we have many facilities.

Unidentified speaker

We have over 400 buildings, and they are old.

Unidentified speaker

So the average age of our firehouses is approaching 100 years old.

Unidentified speaker

And so our state of good repair needs have exceeded our budget.

Unidentified speaker

I think we are seeing the budget move in the right direction.

Unidentified speaker

So this plan includes an additional $24 million for roofs.

Unidentified speaker

And, you know, we have also seen that our capital funding for facilities over the last five years has nearly doubled.

Unidentified speaker

We've seen significant adds to our budget over the last five years.

Joann Ariola

Yet many firehouses remain in disrepair, a few of which, and a number of you, our commissioner, our chief, and certainly Paul, we were out there looking at them.

Joann Ariola

So how can you...

Joann Ariola

take this pool of funding that is pushed into the out years and encourage the administration to bring that funding forward.

Unidentified speaker

So we do have conversations with OMB about project accelerations, and the executive budget did include some funding accelerations on the facility side.

Unidentified speaker

It included accelerating $11.7 million into next year for renovations at one of our fleet maintenance buildings, which will expand capacity.

Unidentified speaker

It included accelerations of $1.7 million into 27 and $10.1 million into 28 for multi-component renovations at EMS Station 4.

Unidentified speaker

It included $10.5 million into FY27 to replace the apparatus for Engine Company 163, and $6.8 million into FY27 to replace air compressors at our mask services unit.

Unidentified speaker

I think there are lots of projects that we're looking at to see if there's a potential for acceleration.

Unidentified speaker

Bandwidth is a part of this, too.

Unidentified speaker

So the additional civilian headcount that was added in this plan will be incredibly beneficial towards getting more projects done.

Unidentified speaker

So that will allow us to hire more trade staff and facilities to make repairs.

Unidentified speaker

We'll help with our project management capability.

Unidentified speaker

We'll help with procurement.

Unidentified speaker

So we've lost a lot of procurement staff, and adding back some of those folks will help get those design and construction.

Unidentified speaker

Construction contracts that we need to get that capital work moving done faster.

Joann Ariola

Okay, so.