Shulman asks about construction duration for Queens Boulevard project
New York City Council · Oct 6, 2026 · starts 1:06:02 · 20 sec
Shulman asks how long construction will take; Loeb says full completion will take about 30 to 36 months, with the building enclosed after about two years.
Lynn C. Schulman
And how long will construction take?
Member of the Public - Rachel Loeb
Push the wrong button, sorry.
Member of the Public - Rachel Loeb
This building, it will be approximately 30 to 36 months for full completion.
Member of the Public - Rachel Loeb
But once, after about two years, it's fully enclosed and they're just finishing the interiors.