Chair Riley asks how DCP will assess infrastructure without environmental review

New York City Council · Oct 21, 2026 · starts 0:28:10 · 1 min 34 sec

He asks how DCP will be informed on open space, sewer capacity, school seats, etc., when projects skip environmental review; Garodnick explains the SEQRA exemption for modest projects and that land use review still applies.

Kevin C. Riley

With the changes to SEEKER, many private applications will skip environments.

Kevin C. Riley

With our environmental review, how would DCP be informed on whether there is sufficient open space, sewer capacity, school seats, pre-K availability, public transportation access, and other infrastructure to support development?

Dan Garodnick

Thank you for your question.

Dan Garodnick

So there are a subset of projects now that are exempt from CCRA based on recent passage

Dan Garodnick

at the state level, which really is exempting projects that are relatively modest, 250 units to low to mid-density districts, 500 in higher density districts.

Dan Garodnick

This exemption really came from a 10-year analysis that showed us that across all of these projects, less than 1% produce an environmental impact.

Dan Garodnick

And so these were projects that were previously really held in about two years of review where there was no impact produced, which obviously is adding time and cost.

Dan Garodnick

Based on our analysis, we saw that it added over $80,000 in additional cost per unit.

Dan Garodnick

And so we will certainly continue to move those projects forward as they are seeker exempt, but they are still subject to land use review, right?

Dan Garodnick

That does not change.

Dan Garodnick

The ULERT process doesn't change either.

Dan Garodnick

And so questions about high density, bulk, all of the relation to the neighborhood, public realm, those questions will still come up and are part of our land use review process.

Dan Garodnick

What has changed, however, is the EAS process, which, again, based on 10 years of analysis, was not producing an impact or requiring mitigation.