Sanchez asks how DOB verifies stop work order corrections

New York City Council · Oct 21, 2026 · starts 1:49:07 · 2 min 27 sec

Sanchez asks whether DOB returns to confirm corrective work after a stop work order; Tigani explains owners must submit means-and-methods analysis and a corrective action plan that DOB reviews before lifting the order, and Shamash adds the department does not blindly accept remediation plans and re-inspects immediately hazardous violations through its hazardous re-inspection program.

Pierina Ana Sanchez

So I thought I had it somewhere, but I'm going to just ask it off the top of my head.

Pierina Ana Sanchez

For these full stop work orders, stop work orders, I'm understanding from your opening testimony, Commissioner, and from your answer just now, Deputy Commissioner, that the agency essentially keeps going back to see if

Pierina Ana Sanchez

dangerous conditions have been corrected.

Pierina Ana Sanchez

Is that the case?

Ahmed Tigani

I would just amend this.

Ahmed Tigani

So if there is a partial stop work order or a full stop work order, the contractor, responsible person, the owner, knows that they have a responsibility to provide us with a means and method analysis and a corrective action strategy.

Ahmed Tigani

Related to the issue that brought on that violation and action.

Ahmed Tigani

Once that is submitted to the department and reviewed, and if an inspection is required, an inspection, then we'll take the steps to lift that partial or full stop work order.

Ahmed Tigani

But there is a process that's involved, and it's contingent on the owner to demonstrate that they understand what was wrong, they corrected what was wrong, and they'll allow them to move forward.

Pierina Ana Sanchez

So they submit to you means and methods.

Pierina Ana Sanchez

They submit to you what their corrective action plan is, and then you accept that in every case you go back and check that they're doing the work correctly?

Yegal Shamash

I'll just add one other statement.

Yegal Shamash

If we don't hear back and it is an immediately hazardous violation, we will re-inspect as part of our hazardous re-inspection program.

Yegal Shamash

So if we do not hear back from them, we will re-inspect.

Yegal Shamash

To answer your question just now, no, we don't just blindly accept their remediation plan.

Yegal Shamash

We have a whole team at the department that reviews any kind of documentation related to stop work orders.

Yegal Shamash

You know, depending on what the remedy is in the violations, it could be a litany of things that need to get submitted to us.

Yegal Shamash

And then we go and review the corrective action that has taken place on site to make sure it has been implemented and an inspector will go out and confirm that.

Pierina Ana Sanchez