Council Member Dinowitz on $36M Tracy Towers capital plan and permit delays

New York City Council · Jul 15, 2026 · starts 2:15:00 · 2 min 40 sec

Dinowitz asks about the $36M capital plan for Tracy Towers, when work begins, and what HPD can do to expedite permits. Phillips says work should start in the next couple months and HPD communicates with DOB to expedite. Dinowitz urges faster action given shed costs.

Eric Dinowitz

for the betterment of the residents of our Michelama developments, we should be all beginning those documents.

Eric Dinowitz

And if it's happening at Tracy, it's happening at all of the Michelamas and many of the Michelamas around our city where work is done and there's no oversight as to the quality of work.

Eric Dinowitz

Now, there is a $36 million capital plan.

Eric Dinowitz

I believe the work was, when you came to visit, the work was supposed to start in June.

Eric Dinowitz

Is that correct?

Adam Phillips

The loan closing was in June.

Eric Dinowitz

Loan closing.

Eric Dinowitz

And when does the work begin?

Adam Phillips

So probably in the next couple months, I would say.

Adam Phillips

For any construction project, Mitchell Lama or not, after construction loan closing, there's a period where the construction crew and the contractor will continue to pull permits, continue to get all their paperwork in order, and then mobilize to be able to start.

Adam Phillips

Construction work.

Adam Phillips

And that's typical across every project.

Eric Dinowitz

Given that this is under the city-run Michelama, what can HPD do to expedite those permits to make sure that work is done in a more timely fashion than we typically see in our offices?

Adam Phillips

So sometimes, and I'm not 100% familiar with this project, but in some circumstances, and a lot of circumstances, we require permits to be pulled prior to closing.

Adam Phillips

I don't know exactly which permits need to be pulled for this project, but we make every effort with all of our affordable housing projects to ensure we're communicating with DOB and that our projects are getting permits pulled quickly.

Eric Dinowitz

We see, and I'm glad Amalgamated is here, we see a lot of costs.

Eric Dinowitz

because of delays of things like permits or in their cases, DOB inspectors coming in.

Eric Dinowitz

And again, I understand it's not your agency, but you work in the same administration, you work in the same government.

Eric Dinowitz

And so you should be doing everything for our affordable housing to expedite those processes.

Eric Dinowitz

Otherwise,

Eric Dinowitz

My office tries to do it, but we're a different branch of government.

Eric Dinowitz

You are in the same branch of government as these other agencies.

Eric Dinowitz

And that is a way to make sure the residents of our Mitchell Llamas and our limited equity co-ops can get the housing they deserve and save money, in their case, by not having those sheds up for...

Eric Dinowitz

Months and months on end.

Eric Dinowitz

And that was the case at Tracy Towers, by the way, in the late 2010s, when they had their sheds up for years.

Eric Dinowitz

It was years, and it wasn't until the controller called, made a call in, and it was gone.

Eric Dinowitz

These are just bureaucratic hurdles that cost residents money.

Adam Phillips

Part of the speed report that was released tries to get to the root of some of those problems, is to kind of get out of our own way to make sure we can do development much more quickly and much more transparently.

Adam Phillips

So speed was a big attempt at moving that forward.