Zhuang asks how much city capital funding goes to OAC repairs

New York City Council · Oct 27, 2026 · starts 2:22:47 · 2 min 29 sec

Zhuang asks about large city capital funding for NYCHA, such as $221.9 million for lead abatement in FY27, and whether any is used for OAC repairs. Trimble says those line items are mostly for apartments, not community centers. Community centers primarily benefit from direct allocations from elected officials, not NYCHA's capital plan.

Susan Zhuang

I have some questions about the budget.

Susan Zhuang

A large amount of city capital funding at NYCHA received goes towards lump sum projects such as lead abatement, which funded at $221.9 million in fiscal 2027

Susan Zhuang

adopted budget.

Susan Zhuang

Other examples of these are asbestos abatement.

Susan Zhuang

Comprehensive approach to mold, general construction, and the building improvement.

Susan Zhuang

We want to know which and if there's a large part for capital funding are being used for facilitate repairs in older adult centers.

Eva Trimble

Thank you, Council Member.

Eva Trimble

For the most part, those line items you're referencing are for our apartments and not for our community centers.

Eva Trimble

As I mentioned earlier, the community centers primarily benefit from direct allocations from elected officials in the council or state or federal partners.

Eva Trimble

They are not part of our capital plan.

Susan Zhuang

So even you get the money, you guys are not going to improve any senior center.

Susan Zhuang

Even in the same building, you are doing second floor, you will not do first floor.

Eva Trimble

The centers obviously benefit from work we're doing on our buildings.

Eva Trimble

If we're repairing our roofs, if we're repairing our heating systems, if we're doing building line initiatives for replacement of plumbing stacks, centers in those buildings would benefit from it.

Eva Trimble

But the...

Eva Trimble

Those funding lines that you mentioned are primarily for the benefit of our apartments.

Eva Trimble

Okay.

Susan Zhuang

Will you guys do anything for the community center?

Abigail Fradkin

Yeah, I can add to that.

Abigail Fradkin

So those are, as Eva mentioned, the direct allocations from city council members, other elected officials are going directly to older adult center comprehensive renovations.

Abigail Fradkin

We have completed seven of those, primarily city discretionary funded in the last year and a half.

Abigail Fradkin

We have 16 active projects with a total budget of $57 million, and we have six planned that are currently in discussion around funding.

Abigail Fradkin

So across those completed active planned, that covers about 30 of our Section 9 older adult centers currently in our portfolio.

Abigail Fradkin

But that is separate from the...

Abigail Fradkin

The city funding that you mentioned, the city funding lines that you mentioned.